> I want to use gant.tex to give me a time line like:
> 
>                         2008                              2009
>        |     Jan - Feb   |   Mar - Apr  | ...   |  Jan -Feb | ....
>        |____________________________________________________________
> Task 1 |
>        |
> Task 2 |
>        |
>   '''  |
> 
> But I can't do this because the \psk at GanttChartIntervalname is fixed as
> Week, Montt, etc., and then incremented as Week 1, Week 2, ....

This needs a lot of modifications in the code.
The easiest way is to skip the default interval names,
using a temporary \psgrid and then \rput for setting
your specific header.

Herbert